Quantity calculator

Concrete Volume Calculator

Work out the concrete volume for slabs, footings, beams and columns, then get cement bags, sand, aggregate and water for your mix grade.

Inputs
m
m
m
%

Nominal mixes for site batching. Ready-mix orders only need the wet volume.

ResultM20
Concrete volume incl. wastage 0m³ 0 yd³ · 0 ft³
Net volume (no wastage)
–
Cement
–
Sand
–
Aggregate (20 mm)
–
Water (w/c 0.50)
–
Ready-mix trucks (9 m³)
–
Show working

How to calculate concrete volume

Concrete is ordered and priced by volume. For any rectangular element, multiply its three dimensions in the same unit, then multiply by the number of identical elements.

Slab / beam: V = L × W × D × n
Circular column: V = π × (d ÷ 2)² × H × n

Add a wastage allowance for spillage, uneven sub-base and over-break. Most site engineers use 3–5% for slabs and beams and up to 10% for footings cast against excavated ground.

How cement, sand and aggregate are worked out

Wet concrete loses volume when the voids between particles fill with paste. To get the dry materials, multiply the wet volume by a dry volume factor of 1.54, then split it by the mix ratio.

  1. Dry volume = wet volume × 1.54
  2. Sum of ratio parts, for example M20 = 1 + 1.5 + 3 = 5.5
  3. Cement volume = dry volume × 1 ÷ 5.5, then × 1,440 kg/m³ for mass
  4. Bags = cement mass ÷ 50 kg
  5. Sand and aggregate follow the same split using their ratio parts

Worked example

A 10 m × 6 m slab, 200 mm thick, in M20 with 5% wastage: 10 × 6 × 0.2 = 12 m³, plus 5% = 12.6 m³. Dry volume is 12.6 × 1.54 = 19.40 m³. Cement is 19.40 ÷ 5.5 × 1,440 = 5,080 kg, or about 102 bags. Sand is 5.29 m³ and aggregate 10.58 m³.

Typical thicknesses

ElementTypical depthCommon grade
Blinding / lean concrete50–75 mmM10
Ground floor slab on grade100–150 mmM20
Suspended floor slab150–250 mmM25 and above
Isolated footing300–600 mmM25 and above

Structural grades above M25 are designed mixes (by weight) from a ready-mix supplier, not nominal volume ratios. Always follow the project specification and the structural engineer's drawings.

Frequently asked questions

How many bags of cement are in 1 m³ of M20 concrete?

About 8 bags of 50 kg. The dry volume is 1.54 m³, cement is one part in 5.5, giving 0.28 m³ × 1,440 kg/m³ ≈ 403 kg.

Why multiply by 1.54?

Loose dry materials contain air voids and bulk when stacked. Around 54% extra dry material is needed to produce one cubic metre of compacted wet concrete.

How do I convert m³ to cubic yards?

Multiply cubic metres by 1.308. One cubic yard is 0.7646 m³ or 27 ft³.

How much wastage should I add?

3–5% for formed slabs and beams, 5–10% for footings and pile caps cast against earth, and more for small, scattered pours.