How the estimate works
Project budget = construction cost × (1 + design % + approvals % + contingency %) × 1.05 VAT
This is a budget estimate for the early stage of a project, before drawings are priced. It multiplies the built-up area (every floor, measured to the outside of the walls) by a cost per square metre for the type of building and finish, then adds the costs that sit on top of construction: designers and site supervision, authority approvals and connection fees, a contingency for the unknowns, and VAT. Once you have drawings, price the actual quantities in the BOQ Builder instead.
UAE construction cost per m² (2025 benchmarks)
| Building type | Standard | Mid-range | High-end |
|---|---|---|---|
| Villa | AED 4,200/m² ≈ AED 390/sq ft | AED 7,000/m² ≈ AED 650/sq ft | AED 11,000/m² ≈ AED 1,020/sq ft |
| Apartment building | AED 4,300/m² ≈ AED 400/sq ft | AED 6,500/m² ≈ AED 600/sq ft | AED 9,500/m² ≈ AED 880/sq ft |
| Office / commercial | AED 5,500/m² ≈ AED 510/sq ft | AED 6,400/m² ≈ AED 595/sq ft | AED 7,300/m² ≈ AED 680/sq ft |
| Warehouse (pre-engineered steel) | AED 2,000/m² ≈ AED 185/sq ft | AED 2,500/m² ≈ AED 230/sq ft | AED 3,000/m² ≈ AED 280/sq ft |
The standard and high-end villa, apartment and commercial figures are the Dubai averages for the second quarter of 2025 in Knight Frank's UAE construction review. Mid-range figures sit between them, and the warehouse range reflects contractors' published rates for pre-engineered steel buildings. Treat all of them as starting points: a quantity surveyor's estimate from drawings will always be more reliable.
Worked example
A 450 m² mid-range villa at AED 7,000/m² is AED 3,150,000 to build at mid-2025 prices, or AED 3,307,500 after 5% escalation. Adding 6% design and supervision, 2% approvals and 10% contingency gives AED 3,902,850, and 5% VAT brings the project budget to about AED 4.1 million, or roughly AED 9,100 per m² all-in.
Where the money goes
For a typical villa or apartment building, the structure (foundations and frame) takes about 35–40% of the construction cost, mechanical, electrical and plumbing works about a quarter, and finishes about a fifth. The higher the finish level, the bigger the finishes share becomes. Warehouses are different: the steel frame and cladding are close to half the cost.
Frequently asked questions
How much does it cost to build a villa in Dubai per square foot?
Roughly AED 390 per sq ft for a standard villa, about AED 600–850 for mid-range finishes and AED 1,000 or more for high-end villas, for construction alone. Design fees, approvals, contingency and VAT add about 20–25% on top.
What is included in the cost per m²?
The construction contract: foundations, structure, blockwork, roofing and waterproofing, MEP services, internal finishes and basic external works. Land, furniture, appliances, landscaping beyond the basics, and finance costs are not included.
How do I convert cost per sq ft to cost per m²?
Multiply by 10.764. For example, AED 400 per sq ft × 10.764 = AED 4,306 per m². To go the other way, divide by 10.764.
How much contingency should I allow?
About 10% at the concept stage, dropping to 5% once the design is complete and priced. Renovations and projects on difficult ground need more.
Is VAT charged on construction in the UAE?
Yes. Construction services are generally subject to the standard 5% VAT. Some first supplies of new residential buildings can be zero-rated, so check your case with a tax adviser.