Project planning

Manhours and Labour Cost Calculator

Work out total manhours and labour cost for a crew, including overtime. Or go the other way: from a quantity and a productivity rate, find the manhours and the number of workers needed to finish on time.

Also known as: man-hour calculator, manpower calculator, labour cost calculator, overtime calculator UAE, crew size calculator.

Inputs
nr
days
h
h
AED

Productivity example: a mason pair laying 10 m² of 200 mm block in 8 hours is 10 ÷ 16 = 0.63 m² per manhour. Use your own site records where you have them.

Result–
Total manhours 0 –
Show working

Manhours, manpower and labour cost

A manhour is one worker working for one hour. Planners use manhours to price labour, check progress and size crews. The arithmetic is simple, but overtime and site efficiency are easy to forget.

Manhours = workers × days × hours per day
Labour cost = normal hours × rate + overtime hours × rate × OT multiplier
Manhours needed = quantity ÷ productivity ÷ efficiency
Workers needed = manhours needed ÷ (days × hours per day)

Worked example: crew cost for a month

12 workers, 26 days, 8 normal hours plus 2 overtime hours a day, at AED 12 an hour with overtime at 1.25 ×. Normal hours = 12 × 26 × 8 = 2,496. Overtime hours = 12 × 26 × 2 = 624. Cost = 2,496 × 12 + 624 × 12 × 1.25 = 29,952 + 9,360 = AED 39,312.

Worked example: crew size for blockwork

1,800 m² of blockwork at 1.25 m² per manhour needs 1,440 productive manhours. At 85% efficiency that becomes 1,694 paid manhours. Over 20 days of 10 hours, that is 1,694 ÷ 200 = 8.5, so plan 9 workers.

Overtime in the UAE

Under the UAE Labour Law (Federal Decree-Law No. 33 of 2021), overtime is normally paid at the basic hourly wage plus at least 25%. Work between 10 pm and 4 am, or on a rest day without a substitute day off, is paid at plus at least 50%. Overtime is generally limited to 2 hours a day. Check the current rules and your contracts before relying on these figures.

Frequently asked questions

What is the difference between manhours and man-days?

A man-day is one worker for one working day. With 8-hour days, 1 man-day = 8 manhours. Always state the hours per day when quoting man-days.

What site efficiency should I use?

Not every paid hour is productive. Breaks, setting up, waiting for materials and weather all reduce output. 80–90% is a common planning range. Use lower values for hot-weather work or congested sites.

Should overtime count in manhours?

Yes, every hour worked counts as a manhour. Only the cost changes, because overtime hours are paid at a higher rate.

Written and checked by Ahmad Azhar, Construction Engineer with more than 20 years on high-rise, mall, villa and airport projects. Last reviewed November 2026.