How working days are counted
The calculator walks through every date in the period. A date is a working day unless it falls on your weekend, on a public holiday in the calendar you chose, or on a date you entered yourself. A holiday that falls on a weekend is counted once, as a weekend day.
Worked example
From Monday 2 November 2026 to Friday 27 November 2026 there are 26 calendar days. With a Saturday–Sunday weekend, 6 of them are weekend days, leaving 20 working days. If the client closes the site for one day, enter that date in your own holidays and the answer drops to 19.
Which weekend should I choose?
Most of the world works Monday to Friday with a Saturday–Sunday weekend. Some countries in the Middle East and Asia use Friday–Saturday or Friday only, and many construction sites everywhere work a six-day week. Pick the pattern written in your contract or approved programme, because it changes the finish date considerably on long durations: 120 working days is about 24 weeks on a five-day week but only 20 weeks on a six-day week.
Public holiday calendars
- United Arab Emirates: the official list under Cabinet Resolution No. 27 of 2024 for 2026, with expected dates for 2027. Islamic holidays follow moon sighting and can move by a day, so check official announcements before you fix a programme.
- United Kingdom (England and Wales): the eight regular bank holidays, worked out for any year, including Easter and substitute days when Christmas, Boxing Day or New Year falls on a weekend. Scotland and Northern Ireland have different holidays; add them in your own list. One-off extra bank holidays announced by the government must also be added by hand.
- United States: the eleven federal holidays for any year, moved to the Friday or Monday when they fall on a weekend, as the federal government observes them. State holidays and company holidays vary; add them in your own list.
- Any other country: choose "None" and type your national holidays in the box. You can paste a whole list, one date per line, or use ranges such as 2026-12-24 to 2027-01-01 for a year-end shutdown.
Using working days in a construction programme
Planning tools such as Primavera P6 and MS Project schedule activities on a calendar that holds the weekend pattern and holidays. Use this calculator to check activity durations, extension-of-time claims or look-ahead dates against the same calendar. Shorter working hours, such as summer or religious-month hours in some countries, affect productivity but not the count of working days.
Frequently asked questions
Does the calculator include the start and end dates?
Yes. Both dates are counted, the same way a P6 activity that starts and finishes on the same working day has a duration of one day.
What happens if a holiday falls on a weekend?
It is counted once, as a weekend day. UAE holidays falling on a weekend are not moved to another day unless the Cabinet announces a change.
My country is not in the holiday list. What do I do?
Choose "None" and type your national public holidays in the "Your holidays and shutdowns" box, one per line or separated by commas. Your government's official holiday list is the best source.
Are private sector holidays the same as government holidays?
Not always. In the UAE the official list has applied to both sectors since 2024; in many other countries companies set their own. Individual employers may still grant extra days, which you can add as extra non-working dates.
Why are some UAE dates marked as expected?
Eid and other Islamic holidays follow the lunar Hijri calendar. The final dates are confirmed after moon sighting, usually a few days before.
Written and checked by Ahmad Azhar, Construction Engineer with more than 20 years on high-rise, mall, villa and airport projects. Last reviewed November 2026.