The five percentage formulas
A as a % of B = A ÷ B × 100
% change = (B − A) ÷ A × 100
N plus X% = N × (1 + X ÷ 100) · N minus X% = N × (1 − X ÷ 100)
Original before X% added = Final ÷ (1 + X ÷ 100)
Examples from site and the office
Retention on an interim payment
An interim certificate is AED 450,000 and retention is 10%. Retention = 450,000 × 10 ÷ 100 = AED 45,000, so the net payment is AED 405,000.
Progress percentage
1,350 m² of blockwork is built out of 1,800 m². Progress = 1,350 ÷ 1,800 × 100 = 75%.
Price increase
Rebar went from AED 2,600 to AED 2,860 per tonne. Change = (2,860 − 2,600) ÷ 2,600 × 100 = +10%.
Price before markup
A subcontractor's price of 1,150 includes a 15% markup. The cost before markup was 1,150 ÷ 1.15 = 1,000, not 1,150 − 15% = 977.50.
Frequently asked questions
Why can't I just subtract the percentage to remove a markup?
Because the markup was calculated on the smaller, original number. Adding 15% then taking 15% off does not get you back to the start. Divide by 1.15 instead.
What is the difference between markup and margin?
Markup is profit as a percent of cost. Margin is profit as a percent of the selling price. A 25% markup equals a 20% margin.
How do I work out 5% VAT?
Use the add option with 5%, or the dedicated VAT calculator, which also removes VAT from a total.
Written and checked by Ahmad Azhar, Construction Engineer with more than 20 years on high-rise, mall, villa and airport projects. Last reviewed November 2026.