Hoover Dam holds about 2.5 million cubic metres of concrete. If it had been placed as one continuous pour, engineers calculated that it would have taken around 125 years to cool, and the stresses from that slow cooling would have cracked the dam apart. The way they solved the problem is still the basis of mass-concrete work today.
Why concrete gets hot
Concrete does not dry. It hardens through a chemical reaction between cement and water, called hydration, and that reaction releases heat. In a thin slab the heat escapes into the air. In a block many metres thick it is trapped. The core expands while it is hot, then shrinks as it cools, and the difference between the warm inside and the cool outside pulls the concrete apart.
Hundreds of blocks instead of one pour
The dam on the Colorado River stands 221 metres tall. The first concrete was placed in June 1933. Rather than one mass, it was built as a stack of separate columns, some as large as 15 metres square. Each lift of fresh concrete was only about 1.5 metres deep, so a good part of the heat could escape before the next lift went on top.
A refrigerator inside the dam
That alone was not enough. Before each lift, crews laid loops of 25 mm steel pipe on the surface. In total more than 900 kilometres of pipe were cast into the dam. River water was pumped through first, followed by chilled water from a refrigeration plant built on site. When a block had cooled and finished shrinking, the pipes were cut off and pumped full of grout, and so were the joints between the blocks. The result behaves as one solid structure.
Two years early
The last concrete was placed in 1935 and the dam was handed over in 1936, more than two years ahead of schedule. It still holds back Lake Mead today.
The same thinking applies to thick rafts and pile caps on modern sites, including in the Gulf, where hot weather makes the problem worse. Specifications limit the placing temperature and the difference between the core and the surface for this reason.
Mass concrete is a heat problem. Plan the size of each pour, the mix and the cooling before the first truck arrives, because cracks from trapped heat cannot be undone.
Photos via Wikimedia Commons. Hoover Dam concrete columns under construction: Bureau of Reclamation, Public domain, via Wikimedia Commons; High-scalers on Hoover Dam: U.S. National Archives, Public domain, via Wikimedia Commons; Pouring concrete in diversion tunnel No. 3: U.S. National Archives, Public domain, via Wikimedia Commons; Placing side-wall concrete in diversion tunnel No. 2: U.S. National Archives, Public domain, via Wikimedia Commons; Hoover Dam aerial view: Lynn Betts, Public domain, via Wikimedia Commons.
Enjoyed this story? A thumbs-up tells us to write more like it.

