A Skyscraper in 410 Days: How the Empire State Building Went Up

102 floors in 410 days. Steel arrived on a timetable, a railway ran on every floor, and the frame rose four and a half storeys a week.

Watch the 46-second version with narration, or read the full story below.

The Empire State Building has 102 floors and stands 381 metres to its roof. It was built in 410 days. Even with modern cranes and software, few towers of that size have gone up as fast. The speed came from planning the job like a factory production line.

A race in the Great Depression

Construction started in March 1930, a few months after the Wall Street crash. The owners were in a race with the Chrysler Building for the title of tallest in the world, and every month of construction cost money in interest. The contractors, Starrett Brothers and Eken, promised to finish in about a year.

Steel on a timetable

The frame used about 57,000 tonnes of steel. Each beam was rolled in Pittsburgh, marked with its exact position in the building, and delivered on a schedule so tight that some pieces were lifted into place within about 80 hours of leaving the mill. There was almost no storage space on the Manhattan site, so the right piece had to arrive at the right hour.

At its peak the frame rose about four and a half floors a week.

A factory in the sky

The design was drawn so the trades could follow each other upward in a fixed order: steel, then floor slabs, then the outside walls, then services and finishes. A small railway ran on each floor to move materials from the hoists to the workers. Cafeterias were set up on several levels so that the crew, as many as 3,400 people a day, did not lose time going down to the street for lunch.

Photographer Lewis Hine followed the ironworkers up the frame. His pictures of men balancing on beams high above New York became some of the most famous images of construction ever taken.

Early and under budget

The building opened on 1 May 1931, ahead of programme and well under its budget. It remained the tallest building in the world until 1970.

The engineering lesson

Speed comes from planning. Fixed sequences, just-in-time deliveries and short travel distances for workers and materials saved more time than any single machine.

Photos via Wikimedia Commons. Icarus, Empire State Building: Lewis Hine / The Met, CC0, via Wikimedia Commons; Empire State Building girders and workers: Lewis Hine / Preus museum, No known restrictions, via Wikimedia Commons; Jumping the derrick: Lewis Hine / Preus museum, No known restrictions, via Wikimedia Commons; Workman on the framework of the Empire State Building: Lewis Hine / U.S. National Archives, Public domain, via Wikimedia Commons; Zeppelin near the Empire State Building under construction: Nationaal Archief, No known restrictions, via Wikimedia Commons.